Below are the steps for submitting a Facility Improvement Project (also known as a Capital Improvement request). The diagram to the right and the steps listed below reflect the process the Facility Commitee follows to review requests submitted to the Banks School District.

1.  Fill out the Facility Improvement Request Form
2. The Facilities Committee chair reviews Improvement Request
    Form for Long Range Facility Plan. Provides feedback to the
    requester.
    a. Denied if project does not fall within the BSD Long Range
         Facility Plan.
    b. Approved if project fits within the Long Range Facility plan OR            project lifespan is less than the Long Range Facility plan.
3. Once a project is approved by Facility Committee Chair to move 
    forward.
    a. Review Capital Improvement Request Policy 
    b. Submit Capital Improvement Request Form to
        Superintendent 
and Facility Committee Chair. 
4. Facility Committee will review Capital Improvement request
    forms at their monthly meeting and provide any follow-up as
    needed.
5. Facility Committee makes approval/denial recommendation to
    Superintendent.
6. If Superintendent approves, project is brought to the Banks
    School District Board for approval.